The New-Build Construction Process in Ontario, Step by Step

51 Builder project photos — house framing, roofing and structural work

A custom home is a relay race of about a dozen stages, each inspected before the next covers it. Knowing the sequence helps owners read their schedule — and spot early where delays actually come from.

StageWhat happensInspection
Site servicingWater, sewer, hydro, road access, gradingMunicipal connection inspections
ExcavationDig to underside of footing; shoring where needed—
FoundationsFootings, foundation walls, weeping tile, backfillFooting + foundation inspections
Framing & structureFloors, walls, roof structureFraming inspection
EnvelopeRoofing, windows, doors, exterior cladding—
MechanicalsPlumbing, HVAC, electrical rough-insRough-in inspections
Insulation & drywallInsulation, vapour barrier, board and finishInsulation inspection
FinishesCabinetry, flooring, trim, fixtures, paint—
FinalDeficiency walk-through, occupancyFinal / occupancy inspection

Where builds lose time

  • Unserviced land: construction cannot start until water, sewer, hydro and access exist — servicing lead time is the silent schedule-killer.
  • Inspection gaps: a missed or failed stage inspection idles every trade behind it.
  • Drawing revisions mid-build: trades working from different revisions build the wrong thing, twice.
  • Long-lead finishes: cabinets, windows and fixtures ordered late arrive after the trades that install them.

51 Builder's answer is structural: we self-perform servicing and excavation so the front of the schedule is ours, run one project manager per build, and distribute issued drawings through a portal so every trade builds from the same current revision.